The works involved:
– Closure of several footpaths and public carparks to facilitate site access and safety.
– Construction of a temporary site access and reinstatement on completion.
– Asbestos removal works.
– Demolition of all buildings onsite.
– Removal of rail track.
– Temporary closure of Buxton Train Station to allow the demolition of several 120ft lighting towers.